Hydroelectric stations on Cère river
On the basis of the RunRiver solution, TEXSYS has developed automation and SCADA system for 2 hydroelectric power stations on the Cère river. The commissioning has be done in October and December 2015.
The feature of these hydro power stations is a high heterogeneity of the turbines (5 in total), in terms of output power and technology.
Installed downstream EDF dams, the entry flow in these stations is extremely variable with a high dynamic. The flow dispatcher of RunRiver is able to optimize the production by privileging the best suited turbines to the current flow conditions.